Toronto offers two facilities connected via a metro ring to provide clients with a wide range of solutions, from colocation to cloud and managed services. The Markham location is our newest Canadian data centre, and has 100,923 sq/ft of premium space that is Uptime Certified Tier III in both design and construction.

 

 

 

 

Announcements

CenturyLink reaches agreement to sell Colocation and Data Centre business.

Take a Virtual Tour of our CH3 Data Centre

Data Centres

Toronto Data Centre Location

Location

TR1: Mississauga, Ontario

Space: 86,758 sf   Power: 6.6 MW

Tech Specs

TR1: Mississauga   Space: 86,758 sf   Power: 6.6 MW

Real Estate Summary

  • Located 25 minutes from Toronto Pearson International Airport
  • One storey building
  • Total building interior (sf) = 83,758
  • Raised floor (inches) = 24 and 30

Electrical Summary

  • Enersource provides power feeds
  • Power density minimum(W/sf) = 150
  • Generator configuration = N + 1
  • Total Power Capacity = 6.6 MW
  • Minimum one fuel replenishing company

Fire Detection and Suppression Summary

  • VESDA provides early warning detection
  • Pre-Action system utilises two detection methods; one ionized and one photo electric detector interlocked with the dry pipe sprinkler system

Mechanical Summary

  • Cooling system configuration = N +1
  • CenturyLink manages temperature and humidity to strict ASHRAE standard

TR3: Markham, ON

Space: 100,923 sf Power: 5 MW

Tech Specs

TR3: Markham, ON   Space: 100,923 sf   Power: 5 MW

Real Estate Summary

  • Located 25 minutes from Toronto Pearson International Airport
  • One storey building
  • Total building interior (sf) = 100,923

Electrical Summary

  • Power density minimum (W/sf) = 150
  • Generator configuration = N + 1
  • Minimum two fuel replenishing companies

Fire Detection and Suppression Summary

  • VESDA provides early warning detection
  • Pre-Action system utilises two detection methods; one ionized and one photo electric detector interlocked with the dry pipe sprinkler system

Mechanical Summary

  • Cooling system configuration = N +1
  • CenturyLink manages temperature and humidity to strict ASHRAE standard

More Locations

Over 60 Data Centre Locations Worldwide

Latest from the EpiCenter Blog

Talking Trends: The Data Centre Industry in 2017

Drew Leonard | January 26,2017

January is often a time to look toward a new year and perhaps find ways to improve from the one prior. It's also a time for people to forecast what might happen in the near year, whether it's a new … Read more…→ The post Talking Trends: The Data Centre Industry in 2017 appeared first on CenturyLink EpiCenter Blog.

Network Diversity: Expanded Options

Chip Freund | January 20,2017

Having a lot of options is usually a good thing, especially when investing a lot of money through a purchase. For example, many people buy cars, but some buy them to fit a family with small children whilst others buy … Read more…→ The post Network Diversity: Expanded Options appeared first on CenturyLink EpiCenter Blog.

CenturyLink Data Centres: Building Carrier Density and Cloud Connectivity

Jonathan Martone | January 18,2017

The best technology likely won't work correctly if it's not operated correctly. You can buy the most expensive computer available, but it won't of much use to you if you don't know how to utilise it. CenturyLink has established itself … Read more…→ The post CenturyLink Data Centres: Building Carrier Density and Cloud Connectivity appeared first on CenturyLink EpiCenter Blog.

CenturyLink
Business
@CenturyLink ENT

Resources

Get Started with Featured Resources and Tools

Get Started
Request Consultation

Request Consultation

Call Us

Call Us

SALES: +44 (0) 207 400 6000 
SUPPPORT: 00 800 72 884 743

Get Connected. See What's Next for Business.